Recent Project Summaries - Continued
NORTH LOGAN WATER DISTRICT
Line Upgrade and Tank Addition

Project Cost: $800,000

Project Funding: Rural Development Grant, KIA Loan

Project Status: Complete by the first of 2003

Reference: Smokey Smotherman, Chairman

The North Logan Water District hired McGhee Engineering, Inc. to assist with designing a project to eliminate various system deficiencies and help to secure project financing. The proposed project involved replacing their existing 100,000 gallon standpipe with a new 250,000 gallon elevated storage tank. The new tank solved the District's pressure and storage volume problems. The new tank provides approximately two days of storage capacity at average demand, a substantial improvement over the 18-20 hours of storage currently available. The new tank was constructed approximately 40 feet taller than the former tank, which increased static pressures by 17 psi, assuring that all areas served maintain the required minimum pressures. Also included was the replacement and 8" upgrade of the 6" main transmission line, plagued by poor quality and installation. The total cost of the project was $800,000.
CITY OF WHITE PLAINS, KY
Sanitary Sewer System

Project Cost: $2,750,000

Project Funding: Community Development Block Grant, Rural Development Grant, KIA's SRF Loan, & Local Contribution.

Project Status: Substantially Complete in July 2002

Reference: Mayor Ronnie Lewis

White Plains is a city in Hopkins County with a population of approximately 600 that was formerly without sanitary sewer service. McGhee Engineering, Inc. and the Pennyrile Area Development District helped White Plains secure a grant and low interest loan package for a new sewer collection system to serve the City. Wastewater is pumped to the Nortonville wastewater treatment plant for disposal. The project included over 12 miles of gravity sanitary sewer, a sewage pumping station, 3 miles of forcemain and nearly 350 sewer taps.

 

 

CONTINUED

CITY OF GUTHRIE, KY
Walking Trail & Pedestrian Bridge

Project Cost: $120,000

Project Funding: Pennyrile RC&D T21 Grant & Local In-kind Contributions.

Project Status: Complete in July 2003

Reference: Mayor Scott Marshall

Guthrie desired to improve its pedestrian access to the Tiny Town area, west of downtown. In order to do so, a concrete walking trail and lengthy creek crossing were needed. The City hired McGhee Engineering to design and administer the project. The project included the design, fabrication and erection of an 80' long steel truss bridge as well as the placement of nearly 4,000 linear feet of concrete sidewalks. The project included various items to improve drainage along the trail including curb and gutter as well as miscellaneous culverts and headwalls.