Recent Project Summaries -
Continued
NORTH
LOGAN WATER DISTRICT
Line
Upgrade and Tank Addition
Project Cost: $800,000
Project Funding: Rural Development Grant, KIA Loan
Project Status: Complete by the first of 2003
Reference: Smokey Smotherman, Chairman
The North Logan Water District hired McGhee Engineering,
Inc. to assist with designing a project to eliminate various system deficiencies
and help to secure project financing. The proposed project involved replacing
their existing 100,000 gallon standpipe with a new 250,000 gallon elevated
storage tank. The new tank solved the District's pressure and storage volume
problems. The new tank provides approximately two days of storage capacity
at average demand, a substantial improvement over the 18-20 hours of storage
currently available. The new tank was constructed approximately 40 feet taller
than the former tank, which increased static pressures by 17 psi, assuring
that all areas served maintain the required minimum pressures. Also included
was the replacement and 8" upgrade of the 6" main transmission line,
plagued by poor quality and installation. The total cost of the project was
$800,000.
CITY OF WHITE PLAINS, KY
Sanitary
Sewer System
Project Cost: $2,750,000
Project Funding: Community Development Block Grant, Rural
Development Grant, KIA's SRF Loan, & Local Contribution.
Project Status: Substantially Complete in July 2002
Reference: Mayor Ronnie Lewis
White Plains is a city in Hopkins County with a population
of approximately 600 that was formerly without sanitary sewer service. McGhee
Engineering, Inc. and the Pennyrile Area Development District helped White
Plains secure a grant and low interest loan package for a new sewer collection
system to serve the City. Wastewater is pumped to the Nortonville wastewater
treatment plant for disposal. The project included over 12 miles of gravity
sanitary sewer, a sewage pumping station, 3 miles of forcemain and nearly
350 sewer taps.
CITY OF GUTHRIE, KY
Walking
Trail & Pedestrian Bridge
Project Cost: $120,000
Project Funding: Pennyrile RC&D T21 Grant & Local
In-kind Contributions.
Project Status: Complete in July 2003
Reference: Mayor Scott Marshall
Guthrie desired to improve its pedestrian access to the
Tiny Town area, west of downtown. In order to do so, a concrete walking trail
and lengthy creek crossing were needed. The City hired McGhee Engineering
to design and administer the project. The project included the design, fabrication
and erection of an 80' long steel truss bridge as well as the placement of
nearly 4,000 linear feet of concrete sidewalks. The project included various
items to improve drainage along the trail including curb and gutter as well
as miscellaneous culverts and headwalls.